Views:
To submit an Attachment Y Notification of Potential Resource - SCU Changes of Status follow the steps below. You will need to be signed into the Generation Interconnection Application (GIA) Portal. 

For help accessing the portal, see the article How to Access the Generation Interconnection Application (GIA) Portal.

1) Provide project and generator owner information.
 
2) Enter details for the generation resource, generation interconnection service, certifications and facility information. 
 
3) Click Create to add a generator unit. 
 
4) Enter the generator unit details and click Submit.

 
5) When finished, click Submit. 


6) The Application Summary page is a review of all the information you have submitted for your application. Review all the information carefully for accuracy before continuing. 
 
7) When finished reviewing, click Submit. 
 
8) Click Proceed to submit your application to MISO. 
 
9) Upon successful submission, you will be prompted to click OK. 

10) You will be taken to My Projects, where you can view the status of your application at any point in the process. 