Views:
As an Interconnection customer, you are only eligible for Generator Interconnection Facility Studies (GIFS) access. Getting access to GIFS where you can view DPP Cases and Models is a three-step process defined below: 

1) Your name must be listed on the Attachment C Non-Disclosure Agreement Appendix A for a project in the MISO Queue. Instructions on updating the Attachment C to add your name is located here. 

2) An individual Attachment D. A blank Attachment D is located here. Please review, complete, sign and return PDF copy to Generation Interconnection Planning Group.

3) Submit an access request case via the Help Center. Instructions are provided here. Project number is mandatory when requesting access. 
Comments (0)