Views:

The PRMR is calculated using the following equation, by Asset Owner, by Local Resource Zone (LRZ):
 
𝑃𝑅𝑀𝑅𝐿𝑅𝑍= Ξ£ [(πΆπ‘ƒπ·π‘“βˆ’ 𝐹𝑅𝑃+𝐹𝑅𝑆)Γ—(1+𝑇𝐿%) Γ—(1+𝑃𝑅𝑀𝑅𝑇𝑂)]
        πΏπ΅π΄ Where:
PRMRLRZ = Planning Reserve Margin Requirement per LRZ
CPDf = Coincident Peak Demand forecast per LBA
FRP = Full Responsibility Purchase per LBA
FRS = Full Responsibility Sale per LBA
TL% = Transmission Loss Percentage of LBA
PRM RTO = Planning Reserve Margin in Unforced Capacity set by LOLE Studies
 
REFERENCE
BPM-011 Resource Adequacy

 

Level 100 Resource Adequacy

Level 200 Resource Adequacy